CLAIM #64029 · Exxon Mobil Corp (XOM) · 2023Q1 earnings call · Apr 28, 2023 · due Dec 31, 2026

Uaru will provide an additional 250,000 barrels a day of gross capacity with start-up targeted for 2026.

Darren Woods · CEO

PENDING
graded after results covering Dec 31, 2026 are reported

How to check this claim

Look at: Gross production capacity start-up at the Uaru project, Guyana

It came true if: Uaru project achieves start-up (first production) by 2026-12-31, with gross capacity approximately 250,000 barrels per day

Where: Company disclosures (10-K/Q4 earnings call/press release) on Guyana Uaru project status and capacity

In context

l demand. Compared to the first quarter of 2022, we added about 300,000 oil-equivalent barrels per day to global supply, primarily from a 40% increase in production from Guyana in the Permian Basin, increase more than offset our divestments in the expropriation of Sakhalin-1, which we no longer account for, but which importantly remains part of global supply. In addition, our Beaumont refinery expansion reached nameplate capacity in the quarter. This 250,000 barrel a day expansion is the largest US refinery addition in a decade, helping meet society's ongoing need for transportation fuels. Guyana, we're pleased to announce that we reached final investment decisions for Uaru, fifth offshore project, which will bring on even more production from this low-cost, low-carbon intensity resource. Uaru will provide an additional 250,000 barrels a day of gross capacity with start-up targeted for 2026. Earnings in our Product Solutions business benefited from the team's solid operational execution with top quartile turnaround cost and schedule performance during a particularly heavy planned maintenance period. Low Carbon Solutions, we're building momentum across several fronts. In early April, we announced a long-term agreement with Linde to capture, transport and permanently store up to 2.2 million metric tons CO2 annually. Hydrogen, we announced front-end engineering and design contract for the world's largest low carbon hydrogen facility in Baytown, ahead of agreement with SK Group of Korea for offtake of blue ammonia from that facility. As we said during our Low Carbon Solutions spotlight earlier this month, our low carbon projects must be advantaged and deliver competitive returns.